Civil Vote Journal

Saturday, November 28, 2026Sign inSubscribe
CITY · DEVELOPMENT

Pittsburg approves AI data center on former golf course despite resident opposition

The city approved a three-story data center with backup generators after a design hearing, but still needs council approval for power.

Civil Vote Journal City desk · November 23, 2026 5:13 PM EST

Pittsburg has approved a data center project on 22 acres of the former Delta View Golf Course, according to Scot Scoop News. The facility will include a three-story data center, an electrical substation, and 37 backup diesel generators. The city signed off on the design Dec. 11, 2025, at a hearing before the zoning administrator.

The project has drawn significant opposition. A petition against it gathered more than 28,000 signatures, and the controversy has packed Pittsburg City Hall past capacity, Scot Scoop reported. The City Council passed a 45-day emergency moratorium on new data centers, but the project is exempt from it. The moratorium expires Dec. 10 unless extended.

The data center still needs approval from the City Council for a power contract and a permit from the Bay Area Air Quality Management District for its generators, according to Scot Scoop. The city lent the developer $16.8 million for the land, a debt now reduced to $10.5 million, and the city's utility will supply the data center's power.

The project was not secret, but approvals came in separate steps over several years, Scot Scoop found in reviewing 154 public records. The City Council approved a technology park deal in 2019 that would include data centers. In 2024, the council approved a land-use plan, and in December 2025 came the design review.